送变电工程

includes electric power transmission and transformation engineering in the electric power system ranging from transmission lines、 substations and supporting facilities and distribution lines

project

secondary pressure-reducing reconstructing project of ji steel

constructing company

shan steel group

equipping plan

110kv ais transformer station converted to gis one

working range

working drawings and completing drawings

period of project

2011

project introduction

the project has been put into use since november 2011. the outdoor ais transformer station of ji steel was converted to an indoor gis transformer station with 300-meter cable tunnel at the same time, as a pivotal project of secondary pressure-reducing upgrade and reconstruction and cables buried underground.